The project’s targets in terms of schedule and cost at completion from the last project review to date were announced on 19 May 2022 (1):
The schedule and cost of electromechanical works and of final testing were not reviewed at this stage of the project’s lifecycle.
The main Civil works and MEH performance in 2022 were less than expected. Mitigating actions to recover the impact of c. 3-6 months are underway.
At the end of 2022, the actual costs incurred excluding interim interest for the project as a whole(5) stood at £18.7 billion (at nominal values), or £201516.1 billion. The interim interests stand at £960 billion.
At the end of 2022, the Group recorded a loss value of €0.55 billion in respect of the HPC project. This impairment is based on the 100bp increase in WACC between 2021 and 2022 in the UK market context, and on the update of the project schedule and costs. This impairment is reversible (see note 10.8.2 of consolidated financial statements at 31 December 2022).
ONR continues comprehensive regulatory oversight of the HPC project.
In Q4 2022, ONR approved, as part of its flexible permissioning regime, the End of Manufacture and release for transit of the RPV (Reactor Pressure Vessel) from Framatome, St Marcel. Looking forward, permissioning agreement will be needed from ONR for the Installation of the RPV.
In November 2022 there was a tragic fatal incident on site from crush injuries. The associated formal investigation by ONR continues.
The HPC project company, NNB Generation Company (HPC) Limited and the Department of Energy and Climate Change (DECC) agreed, on October 2015, on the full terms of the CfD for HPC, which was approved by the European Commission in October 2014, ruling that the terms complied with EU state aid rules.
The CfD was signed on 29 September 2016 alongside all the other contracts with the UK Government and it is a contract to provide security in respect of revenues generated from electricity produced and sold by HPC through compensation based on the difference between the strike price and the market price, for a period of 35 years from commissioning of Unit 2.
From the plant’s start date, if the reference price at which the producer sells electricity on the market is lower than the strike price set under the terms of the contract, the producer will receive an additional payment. If the reference price is higher than the strike price, the producer will be liable for the difference.
The key elements of the Contract for Difference are:
There is no explicit volume guarantee in the CfD, nor is there a yearly ceiling; however, the contract is protected against change in law risk and any curtailment on the export of electricity so that the project is contractually hedged for these two events.
Beyond the commissioning phase, the return of the euro investment is mainly dependent on fluctuations in sterling and UK inflation, as revenue is generated in sterling and linked to inflation.
HPC project is protected against power market price changes during the CfD period and is exposed to fluctuations in electricity prices beyond the CfD period.
In terms of foreign exchange, c. 1/3 of the project costs are denominated in Euro. This exposes both the project and EDF group to the GBP/EUR exchange rate. Should sterling fall against the euro, the Sterling cost of the project will go up and its return will therefore drop. A hedging strategy has been implemented at project level.
Nevertheless, at EDF group level, a Sterling devaluation will trigger a fall in euro funding requirements and therefore lower Group debt. Given the long-term investment horizon in the HPC project, EDF group has implemented a gradual strategy to cover the risk of an increase in sterling value for its HPC investment.
Contracts for the Funded Decommissioning Programme (FDP) of HPC were signed on 29 September 2016. For detailed explanation of statutory requirement for nuclear operators, see 1.4.5.1.2.2.
Sizewell C is a project to construct a nuclear power station with two EPR reactors at Sizewell in Suffolk, England. The Sizewell C power plant is expected to have a total capacity of 3.26GW, providing electricity to 6 million households for around 60 years.
This project is based on a replication strategy from HPC, replicating as much as possible the HPC design and the HPC supply chain. Sizewell C will benefit from feedback and experience from HPC as well as a developed UK supply chain, which should providemore certainty over schedule and costs. Organisation and collaboration schemes with Hinkley Point C are being analysed to secure the benefits of the replicability of the Hinhley Point C project, while taking into account the difference in governance (% of ownership at term, partners, etc..). Depending on the schemes, the risk of non-compatibility with the project’s deconsolidation objective could significantly increase.
(1) See EDF’s Press release of 19 May 2021 “Hinkley Point C Update”.
(2) Since the beginning of construction, the project has been delayed by 18 months in total, mainly due to the Covid-19 pandemic. See the press release of 27 January 2021.
(3) Costs net of operational action plans, in 2015 sterling, excluding interim interest and at a reference exchange rate for the project of £1 = €1.23.
(4) Based on inflation indexes as of 30 June 2022, the estimated nominal cost at completion could reach £32.7 billion. The real cost remains unchanged.
(5) Costs at the project’s boundaries which is consistent with the Project completion cost.
(6) Terms of the contract are available on the UK government website: https://www.gov.uk/government/publications/hinkley-point-c-documents.