The delivery horizon for the first waste packages was also clarified. It should begin between 2035 and 2040 according to the ANDRA report of October 2022 summarising the consultations on the pilot industrial phase and governance of the Cigéo project, whereas at the end of 2021, producers were working on the hypothesis that the first waste packages would be received in 2031. Consequently, the provision has been updated to reflect this deferred reception date for the first packages, with no significant impact.
On 16 January 2023, ANDRA filed its application for authorisation to create Cigéo (DAC) with the Ministry for the Energy Transition. This step marks the start of a new phase: examination of the project by the ASN, after which the project could be authorised and construction could begin. Based on ANDRA’s latest schedule, the decree authorising creation is now expected for 2027 (instead of 2025 as previously).
The provision established for long-lived medium and high-level waste, also includes €773 million to cover the conditioning and interim storage of long-lived medium-level waste, principally at the ICEDA conditioning and storage facility (Installation de Conditionnement et d’Entreposage des Déchets Activés).
This facility, constructed at the Bugey power plant, received its first waste packages in September 2020 after the ASN authorised its commissioning on 28 July 2020. The ASN’s decision approving and governing the conditioning of long-lived medium-level waste into packages at the ICEDA facility was formally received on 19 July 2021. At the end of 2021 the first waste packages were sealed, in compliance with the authorisations granted and the commissioning schedule. Two waste packaging campaigns were completed in 2022, as expected.
EDF bears full technical and financial responsibility for decommissioning of the basic nuclear facilities (Installations Nucléaires de Base, INB) it operates. The final shutdown and decommissioning process is governed by legal provisions and regulations set out in Articles L. 593-20 to L 593-25 and R.593-65 to R.593-74 of the Environmental Code. It involves the following operations for each INB:
The decommissioning scenario adopted by EDF complies with France’s Environmental Code, which requires as short a period as possible to elapse between final shutdown and dismantling in economically acceptable conditions and in compliance with the principles laid down in Article L. 1333-1 of the Public Health Code (radioprotection) and section II of Article L. 110-1 of the Environmental Code (protection of the environment). The intended end-state is industrial use: the sites will be restored to their original condition and will be reusable for industrial purposes.
The ongoing dismantling operations concern plants that were constructed and operated before the nuclear fleet currently in operation, known as “first-generation” plants, the Superphenix plant, and the Irradiated Materials Workshop in Chinon. These operations cover four different technologies: a heavy water reactor (Brennilis), a sodium-cooled fast-neutron reactor (the Superphenix at Creys- Malville), natural uranium graphite gas-cooled (UNGG) reactors (at Chinon, Saint Laurent and Bugey) and a pressurised water reactor (PWR, at Chooz). For the Fessenheim PWR plant, the dismantling application is currently under examination by the ASN, and the operations completed concern the pre-dismantling phase.
Each of these operations is a first for EDF, and apart from the PWR, they concern reactor technologies for which there is little or no international experience. They therefore require development of new methods and technologies that are riskier than technologies for which feedback already exists. Decommissioning of the PWR is benefiting from past experience (essentially in the US and limited). The Chooz plant also has the specificity of being located in a cave: this means it is also a unique operation, generating experience that is not immediately transposable and involves specific challenges.
Based on the ongoing decommissioning operations at permanently shut-down plants (particularly the experience gained from the Chooz PWR), the studies conducted for the Summary Preliminary Plan for the two 900MW reactors at Fessenheim, and the preparatory work for dismantling of Fessenheim, it was possible at the end of 2021 to establish a detailed reference estimate of future decommissioning costs for the nuclear fleet currently in operation (“second-generation” plants). However, neither EDF nor any other operator has yet begun a decommissioning programme on a scale comparable to the current PWR fleet, and as a result the estimates include both opportunities and risks, especially associated with the scale effect.
The decommissioning provisions cover future decommissioning expenses as described above (excluding the cost of removing waste from the site and storing it, which is covered by the provisions for long-term waste management).
Details of changes in provisions for nuclear plant decommissioning are as follows:
(in millions of euros) | 31/12/2021 | Increases | Decreases | Discount effect | Other movements | 31/12/2022 |
---|---|---|---|---|---|---|
Provisions for decommissioning nuclear plants in operation | Provisions for decommissioning nuclear plants in operation 31/12/202112,680 |
Provisions for decommissioning nuclear plants in operation Increases- |
Provisions for decommissioning nuclear plants in operation Decreases(7) |
Provisions for decommissioning nuclear plants in operation Discount effect500 |
Provisions for decommissioning nuclear plants in operation Other movements(1,048) |
Provisions for decommissioning nuclear plants in operation 31/12/202212,125 |
Provisions for decommissioning permanently shut-down nuclear plants | Provisions for decommissioning permanently shut-downnuclear plants 31/12/20215,050 |
Provisions for decommissioning permanently shut-downnuclear plants Increases273 |
Provisions for decommissioning permanently shut-downnuclear plants Decreases(194) |
Provisions for decommissioning permanently shut-downnuclear plants Discount effect(160) |
Provisions for decommissioning permanently shut-downnuclear plants Other movements- |
Provisions for decommissioning permanently shut-downnuclear plants 31/12/20224,969 |
PROVISIONS FOR NUCLEAR PLANT DECOMMISSIONING | PROVISIONS FOR NUCLEAR PLANT DECOMMISSIONING31/12/202117,730 | PROVISIONS FOR NUCLEAR PLANT DECOMMISSIONINGIncreases273 | PROVISIONS FOR NUCLEAR PLANT DECOMMISSIONINGDecreases(201) | PROVISIONS FOR NUCLEAR PLANT DECOMMISSIONINGDiscount effect340 | PROVISIONS FOR NUCLEAR PLANT DECOMMISSIONINGOther movements(1,048) | PROVISIONS FOR NUCLEAR PLANT DECOMMISSIONING31/12/202217,094 |