Thanks to renewal programmes, scheduled renovation and use of underground lines rolled out by network operators in high-risk climate zones, the frequency of power outages has lowered, leading to a reduction in the average outage time per customer.
2020 | 2021 | 2022 | |
---|---|---|---|
SAIDI (min.)* | SAIDI (min.)*2020 52 |
SAIDI (min.)*2021 56 |
SAIDI (min.)*2022 59.5 |
CAIDI (min.) | CAIDI (min.)2020 76 |
CAIDI (min.)2021 92.5 |
CAIDI (min.)2022 85.9 |
SAIFI (min.) | SAIFI (min.)2020 0.68 |
SAIFI (min.)2021 0.61 |
SAIFI (min.)2022 0.69 |
* SAIDI: System Average Interruption Duration Index; CAIDI: Customer Average Interruption Duration Index; SAIFI: System Average Interruption Frequency Index.
In 2022, the average outage time, excluding transmission incidents and exceptional incidents, was 59.5 minutes (figures are not final). This good result is in line with the target of 62 minutes set in incentive legislation as part of the Tariff for Using the Public Electricity transmission and distribution Networks (TURPE), despite several events that put the resilience of networks to the test. Indeed, the year began with several storms: Eunice (classified as an exceptional event in Nord-Pas-de-Calais and Somme) and Franklin in February, followed by Diego in April. The summer saw thunderstorms (with an impact on aboveground networks) and several high-intensity heatwaves of unprecedented duration (with an impact on underground networks).
In terms of smart grid technology, the 20kV high-voltage network is already smart since it is supervised and equipped with automated power restoration. It has been further improved with the incorporation of smart fault detectors on the aboveground network and remotely operated control mechanisms. These devices are now continuously monitored to ensure they are working properly; software updates can now be carried out remotely. For the LV network, the deployment of smart meters by Enedis now enables us to have a real-time vision of the characteristics of the electricity at the individual customer level. In areas not interconnected with continental Metropolitan France, and outside Europe, Enedis and EDF are continuing to install connected electricity meters, allowing consumers to monitor their electricity consumption.
2020 | 2021 | 2022 | |
---|---|---|---|
Number of smart meters installed (in millions of units)* | Number of smart meters installed (in millions of units)* 2020 32 |
Number of smart meters installed (in millions of units)* 2021 37.6 |
Number of smart meters installed (in millions of units)* 2022 40.6 |
* For the methodology used for this indicator, see section 3.6 “Methodology”.
As of the end of 2022, 40.6 million meters had been installed, including almost 36.6 million in France (1) as well as in the United Kingdom and India.
In 2020, Enedis, in its capacity as distribution network operator, published its roadmap for the transformation of network scaling methods and integration of flexibilities.
The new version of the Contract for Access to the Public Distribution Network (contrat d’accès au réseau public de distribution, CARD) for production installations connected at medium voltage (HTA) (2) was finalised in late 2022 and came into effect on 1 January 2023. It takes into account network flexibility and availability, thus allowing a maximum amount of energy to be dispatched while also factoring in operating constraints and public grid maintenance.
Since end-2021, Enedis may offer an alternative connection offer with power modulation, also known as the Smart Connection Offer, to all high-voltage producers on request.
Enedis is testing a new method for the scaling of renewable energy Regional Network Connection Plans in real-life conditions at 8 source substations in the Landes and Somme regions, the immediate effect of which has been to free up over 200MW of connection capacity as a result of greater flexibility (ReFlex Project).
For the second consecutive year, Enedis has topped the world rankings out of 80 network operators in the Smart Grid Index (SGI) international benchmark, which assesses how “smart” electricity networks are worldwide (3).
Customers receiving high-voltage supply are invited to sign up to a load balancing contract, under the terms of which customers reduce their electricity use as requested by EDF in return for compensation.
The EDF group has several load balancing offers, operated by its subsidiary Agregio:
The storage development strategy launched in 2018 has led to approximately 1.2GW of projects being secured or completed by the end of 2022. In 2022, the Group commissioned battery installations totalling 62MW in Non-Interconnected Zones (NIZs), the UK, and the USA, started construction work on new projects, and expanded the development of projects in the UK and the USA. EDF group storage projects involve pumped-storage hydropower plants (STEPs), hybridisation of batteries with renewable energies, batteries directly connected to the network, and storage with customers.
(1) Scope: Enedis and IES.
(2) Enedis.fr/media/1895/download
(3) www.spgroup.com.sg/sp-powergrid/overview/smart-grid-index