Universal Registration Document 2022

2.2.4 Risks related to operational performance

2.2 Risks to which the Group is exposed

2.2.4 Risks related to operational performance

2.2.4 Risks related to operational performance

4A – Management of large and complex industrial projects including EPR projects (HPC, FLA3, Taishan…)

Summary: The Group carries out very large-scale projects. These projects represent a major risk for the Group in terms of the potential financial impact on its shareholders’ equity and implications for its development strategy. In particular, the success of EPR projects depends on specific industrial, regulatory and financial factors.

Criticality: ●●● Strong

a) Context

As part of its activity and in its capacity as project owner or prime contractor, the Group is called upon to carry out highly complex projects, such as the EPR projects at Flamanville 3 in France and Hinkley Point C (HPC) in the United Kingdom, projects in progress, as well as upcoming projects such as EPR2 in France and Sizewell C. These projects require significant investments and lengthy procedures for enquiries and regulatory approvals.

The success of these projects will determine the future of the nuclear industry sector. These projects represent a major risk for the Group.

The Group’s other major projects under way are:

  • major projects related to the existing nuclear plant (Grand carénage, see risk 5A below, and decommissioning projects);
  • offshore renewable energy projects (off-shore wind power);
  • international hydropower projects.
b) Main risks

These projects are exposed to numerous technical and operational risks relating to their industrial implementation, which could result in start-up delays and an increase in associated costs or a possible reconsideration of certain technical choices. This could ultimately lead to a drop in expected profitability or even to more asset write-downs (see note 10.8.2 to the consolidated financial statements for the fiscal year ended 31 December 2022).

Given their scale, these projects could have a massive impact on the Group’s results and balance sheet, mainly on its equity capital and its financing capacity, and entail major risks for the Group.

There exist other technical, industrial, operational, economic, regulatory, political, environmental or acceptability risks, which could jeopardise project schedules, associated costs and/or profitability.

Risks of technical or operational non-performance,

The technical and operational risks associated with large and complex industrial projects expose the Group to major uncertainties in the implementation and operation of these projects. These risks may have a major impact on the Group’s business, results, asset value, financial position, reputation, organisation and outlook.

By way of illustration:

  • delays in construction or difficulties in the commercial commissioning of the HPC EPR units beyond 31 October 2036 could result in the loss of the revenue protection afforded to these works via the CfD (see section  1.4.5.1.2.5 “Nuclear New Build business”);
  • the conclusions of the ongoing investigation into the June 2021 finding of fuel leakage in a reactor at the Taishan plant were progressively taken on board in other EPR projects (see section 1.4.5.3.6.1 “Activities in China”, and see below, “Operational control of EPR projects”).

In addition to or as a result of these uncertainties, the Group may be in breach of its contractual obligations.

Strategic risks

The Group’s strategic goal is to become involved in the construction of new nuclear facilities in France and abroad. The risk with regard to these projects would be that investment decisions might not be made or might be made under poor technical, regulatory or financial conditions.

Risks related to financing and, where applicable, the regulatory framework

New reactor construction projects, particularly in France and the United Kingdom, require considerable investment, as well as appropriate market organisation, with appropriate financing and pricing conditions. Given the economic or institutional climate or depending on the appropriate progress of the pending projects, obtaining such funding may be delayed or compromised.

In France, inadequate market organisation and the failure to obtain or delays in obtaining the authorisations required to continue the development of the EPR2 reactor, could have an impact on the Group’s financial position, particularly because of the development costs upstream of the decision which might ultimately be borne by EDF. Any event that may delay the launch of the project could lead to disruptions to engineering activities, difficulties in maintaining skills and in mobilising the supply chain, which would be detrimental to the industrial control and performance of the programme.

In the United Kingdom, the new context created by the implementation of Brexit may lead to changes in the conditions for the implementation and profitability of projects and may not allow sufficient conditions to be met for involving investors in the Group’s future projects in the United Kingdom:

  • as the financing needs of the HPC project exceed the contractual commitment of the shareholders (committed equity), the shareholders will be asked to allocate additional equity (voluntary equity). In the event that CGN (the China General Nuclear Corporation) does not allocate voluntary equity capital, it is likely that the Group will be required to contribute those funds in the place of CGN since CGN will have contributed its share of committed equity;
  • for the Sizewell C project, failure to obtain the right financing framework and appropriate regulation could significantly affect the project, and lead the Group to decide not to invest (see next page 2 – “Sizewell C (UK)”).

In addition, the classification as transitional energy under the Taxonomy regulation (see risk 1A) could insufficiently recognise decarbonised nuclear electricity, with potential consequences for access to financing for new projects. The legislation does not include the fuel cycle or waste management. Finally, the conditions set out in the Delegated Act for the classification of nuclear energy as an aligned activity may not be fully met. These elements could influence the Group’s ability to finance future major nuclear projects (see risk 1A).

External risks – political and geopolitical, administrative procedures

All these projects are large-scale and of long duration. They involve numerous industrial partners. Relations with the partners involved with EDF in these projects may also be a source of difficulties.

For example, trade tensions between the United States and China could have an impact on the conduct of some of these projects given the technologies and partnerships implemented (see risk 4B). In the United Kingdom, as EDF and CGN are partners in the HPC and Bradwell projects, these projects could be impacted by the worsening diplomatic relations between the United Kingdom, France, the United States and China, in particular for the Bradwell project led by CGN.