At 31 December 2021, the gross amounts estimated under year-end economic conditions (amounts still to be spent) and the present value of those amounts are as follows, presented by type of reactor technology:
|
31/12/2021 |
(in millions of euros) |
Costs based on year-end economic conditions |
Amounts in provisions at present value |
Pressurised water reactor – PWR – Chooz A |
288 |
259 |
Pressurised water reactor – PWR – Fessenheim* |
829 |
707 |
Natural uranium graphite gas-cooled reactors – UNGG – Bugey, Saint Laurent, Chinon |
5,478 |
3,136 |
Heavy water reactor – Brennilis |
323 |
284 |
Sodium-cooled fast neutron reactor – Superphenix at Creys Malville |
534 |
479 |
*Excluding interim storage and processing of steam generators.
Provisions for decommissioning of permanently shut-down nuclear plants also cover dismantling costs for related facilities such as the APEC Fuel Storage Workshop at Creys-Malville and the BCOT Operational Hot Unit at Tricastin.
Compared to decommissioning costs for the PWR technology, the cost at completion (all costs both settled and remaining) for decommissioning of the other reactors is higher, to different extents depending on their specific characteristics:
- costs are around twice as high for Brennilis (completion cost of approximately €0.88 billion for one reactor) due to its compactness, the fact that the core is encased in concrete and thus difficult to access, the absence of a fuel pool, which complicates remote-controlled segmentation, and the presence of zircaloy (a fire hazard), meaning that segmentation work takes longer and must be more closely supervised;
- costs are around twice as high for UNGG reactors (completion cost of approximately €6.6 billion for six reactors), because they require removal of 20 times more material than a PWR due to their size, and contain graphite which is hard to access and requires special handling such that specific remote-controlled equipment must be developed;
- costs are around four times as high for Creys-Malville (completion cost of approximately €1.8 billion for one reactor), due to processing of sodium for which elimination is very sensitive, and the size of the facilities, especially the reactor (with a vessel 20 times bigger than the vessel of the 1300MW PWR).
The following progress has been made on decommissioning work:
- Chooz A: the reactor was shut down in 1991 and nuclear dismantling began in 2007 after the dismantling decree was issued. The final stage of dismantling began in 2016 and involves segmentation, conditioning and removal of reactor vessel internals, followed by dismantling of the vessel itself. These operations are due to be completed in Under the new full continuous decommissioning scenario, the plant should be declassified by late 2035 (not 2047 as previously expected);
- UNNG reactors: these six reactors were shut down between 1973 and 1994 and received their dismantling decrees between 2008 and 2010 (except for Chinon A1 and A2). Fuel removal and circuit draining have been completed for all these reactors, and dismantling operations are in process for the conventional and nuclear buildings in the periphery of the “reactor caissons”. Following the ASN’s decision of 2020, applications for dismantling permits will be submitted for all these reactors in 2022, to obtain new decrees allowing continuation of dismantling operations according to an “in-air” strategy. Opening of the top part of the first UNGG reactor caisson – Chinon A2 – is expected in 2033: the initial extractions of vessel internals and graphite blocks are due to start in 2040 and last 14 years. In parallel, the other UNGG sites are finalising their work to put the sites into a safe storage configuration (by 2035). A safe storage configuration state means that 80% of surfaces have been dismantled and the reactor caissons awaiting dismantling are safe: this will allow sufficient progress on the first reactor in this series to gain experience and ensure safety for the other five operations. Opening of the caissons after the first UNGG decommissioning is scheduled to take place in or after 2055;
- Creys Malville: this plant was shut down in 1998 and received its dismantling decree in 2006. The following key stages have been completed: removal of the fuel, dismantling of the machine room, drainage of the circuits, processing and elimination of the sodium used for cooling in all circuits, filling the reactor vessel, opening and extracting the vessel caps, and the start of dismantling of the core vessel cap (which weighs several hundred tonnes). The next stages are dismantling the vessel internals (due to be completed in 2026), electromechanical dismantling in the reactor building, then decontamination (dismantling should end in 2038);
- Brennilis: this plant was shut down in 1985 and received a partial dismantling decree in 2011 allowing dismantling of all installations peripheral to the “reactor block”. The following key stages have been completed: removal of the fuel, dismantling of the machine room, the fuel building, auxiliary buildings, heat exchangers and the effluent treatment station. The next stages are examination of the application for full dismantling authorisation, with a view to obtaining a dismantling decree in 2022 that would enable EDF to dismantle the reactor block (the end of these operations is currently forecast at 2040). The public inquiry began on 15 November as planned, and will last 7 The inquiry commissioner is expected to issue his opinion in mid-February 2022.
15.1.1.4 Provisions for last cores
These provisions cover the future expenses resulting from scrapping fuel that will only be partially irradiated when the reactor is shut down. It is measured based on:
- the cost of the loss on fuel in the reactor that is not totally spent at the time of final reactor shutdown and cannot be reused due to technical and regulatory constraints (“front-end” expenses);
- the cost of fuel processing, and waste removal and storage operations (“back-end” expenses). These costs are valued in a similar way to provisions for spent fuel management and long-term radioactive waste
These unavoidable costs are components of the cost of nuclear reactor shutdown and decommissioning. As such, they are fully covered by provisions from the commissioning date and an asset associated with the provision is recognised. In a decision of 11 December 2020, France’s Council of State challenged the tax- deductibility of the consequences of immediate recognition of a provision for dismantling of the last core (“front-end” last core expenses) (see note 17.3.1).
In 2020 after the Fessenheim plant was definitively shut down, €99 million of the provision for last cores, concerning the two reactors at Fessenheim, was reversed with a corresponding reduction in the inventories of non-irradiated fuel in the reactor at the time of the shutdown, and in parallel, provisions for spent fuel management and long-term radioactive waste management were recognised for the cost of processing this fuel and storage of the waste that will result.
In 2021, apart from the effects of extending the depreciation period for 1300MW- series plants at 1 January 2021 (see note 1.4.1), there were few changes in provisions for last cores.