A detailed review of schedule and cost has been concluded in January 2021 to estimate the impact of the pandemic so far. This review has concluded the following(1) :
The project management has set the objective to lift the Unit 1 dome at the end of 2022.
The agreements between EDF and CGN include a capped compensation mechanism between both shareholders in case of cost overruns or delays. Given the expected level of completion costs, this mechanism is applicable and will be triggered when the times comes. EDF’s published IRR takes this compensation mechanism into account(3). This arrangement is part of a Shareholders’ Bilateral agreement signed between EDF and CGN in September 2016 and is subject to a confidentiality clause(see section 2.2.4 “Operational Performance”, risk factor 4A Management of large and complex industrial projects including EPR”).
Despite the impact of the Covid-19 pandemic, major progress has been made in2020 with the overarching priority to protect the construction critical path plan. In particular, the project has achieved 4 important goals set for 2020:
Other major progress has been made on Unit 1. In particular, the 3.5km intake tunnel boring completion and the liner ring 1 successful lift into position in the Reactor building.
On Unit 2, significant progress was also achieved. Works on Unit 2 are carried out circa 12 months after Unit 1.
The UK EPR Design Centre opened in 2020 in Bristol to support the HPC project as well as the development of Sizewell C project (see below “Sizewell C”).
At the end of 2020, the costs to date excluding interim interest for the project as a whole(5) stood at £12.1 billion (at nominal values), or £11.1 billion at real £2015value. The interim interests stand at €518 million.
The ONR has been regularly informed of the management of the Covid-19 situation and the mitigation plans implemented. Next ONR Hold Point will be the start of bulkMEH erection. In addition, agreement from ONR will be needed for the dispatch of the first components coming from Framatome and for the delivery of fuel on site.
The HPC project company, NNB Generation company (HPC) Limited and theDepartment of Energy and Climate Change (DECC) have agreed, on October 2015, on the full terms of the CfD for HPC, which was approved by the EuropeanCommission in October 2014, ruling that the terms complied with EU state aid rules.The Commission’s decision has been challenged by Austria, which sought the annulment of that decision before the General Court of the European Union, which dismissed its action by a judgment of 12 July 2018. On 22 September 2020, theEuropean Court of Justice rejected Austria’s appeal and confirmed the Commission’s decision approving United Kingdom aid for HPC nuclear power station.
The CfD was signed on 29 September 2016 alongside all the other contracts with theUK Government and it is a contract to provide security in respect of revenues generated from electricity produced and sold by HPC through compensation based on the difference between the Strike Price and the market price, for a period of 35 years from commissioning of Unit 2.
From the plant’s start date, if the reference price at which the generator sells electricity on the market is lower than the strike price set under the terms of the contract, the generator will receive an additional payment. If the reference price is higher than the strike price, the generator will be liable for the difference.
The key elements of the Contract for Difference are:
There is no explicit volume guarantee in the CfD, nor is there a ceiling; however, the contract is protected against change in law risk and any curtailment on the export of electricity so that the project is put back in the same position it would have been had the change in law or curtailment event not occurred.
HPC project is protected against power market price changes during the CfD period. Post Cfd, a change in the price of electricity of £2015 10/Mwh has an impact of 0.1%on the IRR.
(1) Assuming the ability to begin a ramp up back to normal site conditions from the second quarter of 2021. Please refer to the Press release of 27 January 2021 “Hinkley Point Cproject update”.
(2) Reminder on the costs previously announced in the Press release of 25 September 2019: £2015 21.5 – 22.5 billion. Costs net of operational action plans, in 2015 sterling,excluding interim interest and excluding forex effect versus the reference exchange rate for the project of £1 = €1.23. Costs calculated on 27 January 2021 (see press release“Hinkley Point C project update”) by deflating estimated costs in nominal terms using the British Construction OPI for All New Work index.
(3) EDF equity IRR calculated at the exchange rate of £1 = €1.13 and including the capped compensation mechanism in place between the project’s shareholders. Previous IRR of7.6% - 7.8% was based on an exchange rate of £1 = €1.15.
(4) Beyond the cost and construction time objectives, this IRR for EDF includes other structuring assumptions. In particular, it is sensitive to inflation rate assumptions andelectricity price assumptions after the CfD period: a 0.1 point change in inflation has an impact of 0.1% on the IRR, a change in electricity prices of £2015 10/MWh post CfD hasan impact of 0.1% on the IRR.
(5) Costs before elimination of intercompany margins which is consistent with the Project completion cost.
(6) Terms of the contract are available on the UK government website: https://www.gov.uk/government/publications/hinkley-point-c-documents.
(7) Low Carbon Contracts Company.