Updating the industrial decommissioning scenario for permanently shut-down power plants, particularly UNGG plants, led to a €590 million increase in the provision at 31 December 2015.
The review of decommissioning provisions for permanently shut-down plants in 2016 led to non-significant adjustments, apart from one increase of €125 million for a specific installation (the Irradiated Materials Workshop at Chinon). In 2017 and 2018, this annual review gave rise to non-significant adjustments.
The amended industrial scenario for dismantling of the UNGG reactors in 2015 was presented to the ASN’s commissioners on 29 March 2016. In 2018 the ASN issued its main questions and conclusions about the UNGG strategy file. A consensus was reached regarding “in-air” dismantling for all reactors, the usefulness of an industrial demonstrator, and the timetable for dismantling the first-of-a-kind reactor (Chinon A2), but discussions continued regarding the dismantling timetable for the other 5 reactors. EDF’s proposed schedule allowed for significant experience-based adjustments (after dismantling the first reactor) before beginning almost simultaneous dismantling of the other 5 reactors. On 12 February 2019, EDF presented all the information justifying the Group’s chosen timetable to the ASN’s commissioners. The ASN then issued draft decisions that were submitted to public consultation between July and November 2019, setting the deadline for filing regulatory applications for authorisation of dismantling work, and the dismantling schedule to be included in the applications. In those draft decisions, the ASN acknowledged that the required operations are complex, and that EDF’s proposed risk control strategy (industrial demonstrator, significant experience with a first reactor) is justified. However, it asked for work on the five reactors after the first-of-a-kind reactor to be brought forward slightly and begin no later than 2055.
In view of the ASN’s draft decisions, the nuclear provisions were increased in 2019 by a total €108 million: €77 million for decommissioning provisions for permanently shut-down nuclear power plants and €31 million for provisions for long-term radioactive waste management (long-lived low-level waste, very low-level and low and medium-level waste).
The ASN’s decisions concerning dismantling of UNGG reactors were published on 17 March 2020 and did not contradict the principles of the draft decisions of 2019. Consequently, the nuclear provisions for decommissioning of UNGG plants were not subjected to any particular reestimation in 2020, and they reflect the best estimate of the industrial and technical scenario.
In 2020, the annual review of the cost estimates for decommissioning of permanently shut-down plants led to a €45 million increase in provisions due to critical path delays following suspension of work during France’s first lockdown phase, and a major unforeseen event associated with suspension of segmentation work on vessel internals at Chooz A. The costs for decontamination of civil engineering work were also updated, leading to a €43 million increase in provisions for the entire scope of permanently shut-down plants.
Finally, in accordance with its powers under Article 594-4 of the Environment Code, in June 2020 the DGEC commissioned an external audit of the valuation of dismantling operations for EDF’s permanently shut-down nuclear facilities, conducted by a consortium of specialist firms. This audit began in December 2020 and will continue until July 2021.
At 31 December 2020, the gross amounts estimated under year-end economic conditions (amounts still to be spent) and the present value of those amounts are as follows, presented by type of reactor technology
31/12/2020 | ||
---|---|---|
(in millions of euros) | Costs based on year-end | Amounts in provisions |
Pressurised water reactor – PWR – Chooz A | Pressurised water reactor – PWR – Chooz A 31/12/2020 215 | 176 |
Pressurised water reactor – PWR – Fessenheim* | Pressurised water reactor – PWR – Fessenheim *31/12/2020 810 | 689 |
Natural uranium graphite gas-cooled reactors – UNGG – Bugey, Saint Laurent, Chinon | Natural uranium graphite gas-cooled reactors – UNGG – Bugey, Saint Laurent, Chinon 31/12/2020 5,352 | 2,967 |
Heavy water reactor – Brennilis | Heavy water reactor – Brennilis 31/12/2020 321 | 276 |
Sodium-cooled fast neutron reactor – Superphenix at Creys Malville | Sodium-cooled fast neutron reactor – Superphenix at Creys Malville 31/12/2020 557 | 494 |
* Excluding interim storage and processing of steam generators.
Provisions for decommissioning of permanently shut-down nuclear plants also cover dismantling costs for related facilities such as the APEC Fuel Storage Workshop at Creys-Malville and the BCOT Operational Hot Unit at Tricastin.
Compared to decommissioning costs for the PWR technology, the cost at completion (all costs both settled and remaining) for decommissioning of the other reactors is higher, to different extents depending on their specific characteristics:
The following progress has been made on decommissioning work: