In 2020, EDF readjusted the cost of the Grand Carénage refurbishment programme for 2014-2025 to € 49.4 billion in current euros(1). For the most part, this new estimation incorporates the first lessons learned for the works to be conducted, drawn from the investigations process during the fourth regular re-examination of 900MW reactors, which was concluded with the ASN decision rendered on
23 February 2021. It includes studies, alterations and additional equipment not originally planned for, aimed at improving safety levels. It also includes the review of the planned duration for scheduled maintenance shutdowns (ten-year inspections and partial inspections), drawing on the experience of previous years, as well as the impact of the health crisis as estimated in 2020, applied to 2020-2022(2).
Under this programme, the planned renovation or replacement of major components of power stations such as generators, transformers or steam generators continue.
At end 2020:
In addition, at 31 December 2020, 55 out of 56 Emergency Diesel Generators were put into operation. The 56th, Paluel 1, was commissioned in February 2021.
Industrial work will continue beyond 2025 on the occasion of the upcoming ten-year inspections. Capital expenditure will therefore remain high beyond 2025.
EDF’s environmental procedure was introduced in 2002 on a few sites, then extended to all nuclear generation units. It is based on an ISO 14001- certified SME environmental management system (see section 3.5.2.5.2 “Environmental management system”).
For a description of radioactive waste processing downstream of the fuel cycle as well as decommissioning, see sections 1.4.1.1.2.3 “The challenges specific to the nuclear activity” – “The nuclear fuel cycle and related issues” and “Decommissioning of nuclear power plants”.
EDF, in its capacity as a nuclear operator, takes responsibility for nuclear safety and, in a rapidly-changing context (market competition, environmental issues, etc.), reaffirms as its absolute priority the protection of the human and environmental health, among other things, through the prevention of accidents and the limiting of their consequences as regards nuclear safety.
The implementation of the French nuclear power programme led EDF to establish a safety procedure that:
Regulatory notice
The French Environment Code (Code de l’environnement) includes specific provisions on the right to information regarding the nuclear industry aimed at guaranteeing the public’s right to reliable, accessible information. In particular, the operator of a BNF is required to declare any accidents and incidents occurring as a result of the operation of the facility that could potentially be detrimental to the interests referred to in Article L. 593-1 of the French Environment Code, namely public health and safety and/or the protection of nature and the environment, and to do so speedily to the ASN and the competent administrative authority.
Other authorities also contribute to transparency for the nuclear industry. They include the Haut Comité pour la transparence et l’information sur la sécurité nucléaire (High Committee for Transparency and Information on Nuclear Safety, HCTISN) as well as local information committees formed for any site housing one or more BNFs.
Nuclear safety is subject to numerous controls, both internal and external.
(1) See the press release dated 29 October 2020 “EDF readjusts the costs of its Grand Carénage refurbishment programme”.
(2) This does not include any subsequent lockdown or other restrictive measures affecting activity.
(3) Follow-up missions related to the recommendations issued during peer-review audits (and detailed in an audit report).