1. The Group, its strategy and activities

Other geographic areas and subsidiaries

At the end of 2019, the Group also has an installed capacity for electricity generation of 33.5GW (with 129TWh of electricity generated in 2019):

  • through EDF Renewables (see section 1.4.1.5.4 “EDF Renewables”) with a consolidated installed capacity of 6GW and output of approximately 15TWh;
  • through overseas departments’ Island Energy Systems and PEI with an installed capacity of 2.1GW and output of approximately 6TWh in 2019 (see section 1.4.4.3 “Island Energy Systems”);
  • through EDF Energy in the UK with an installed capacity of 12.2GW(1) and nearly 60 TWh generated in 2019 (see section 1.4.5.1 “United Kingdom”);
  • through Edison with an installed capacity in electricity of 7GW and 22 TWh generated in 2019(2) (see section 1.4.5.2 “Italy”);
  • in the rest of the world with a consolidated installed capacity of 4GW and output of 22TWh (see section 1.4.5.3 “Other international”);
  • through contribution from Dalkia (see section 1.4.6.1.1 “Dalkia”), excluding heat generation, with an installed capacity in electricity of 2.2GW and output of 4 TWh in 2019.
1.4.1.1 Nuclear power generation in France

The electricity generated by EDF in France from its fleet of nuclear power plants represented 89.8% of its total electricity generation in 2019 excluding pumped storage hydropower.

1.4.1.1.1 EDF's nuclear fleet in France

EDF’s PWR model is divided into three series of available electrical power:

  • a 900MW series consisting of 34 units of approximately 900MW (for a total power capacity of 30,770 MW) with an average age of 38 years;
  • a 1,300MW series consisting of 20 units of approximately 1,300MW (for a total power capacity of 26,370MW) with an average age of 31 years;
  • the N4 series, which is the most recent with an average age of 19 years, consisting of 4 units of approximately 1,500MW (for a total power capacity of 5,990 MW);

for a total of 58 units spread over 19 sites owned by EDF, and constituting a total authorised capacity of 63,130MW as at 31 December 2019. With an average age of approximately 34 years, EDF’s nuclear fleet is about average compared to the fleets installed worldwide.

The commissioning and most recent ten-year inspection (VD) dates for these units as of end-2019 are as follows:

UnitsYear of industrial commissioningMost recent ten-year inspectionNext ten-year inspectionUnitsYear of industrial commissioningMost recent ten-year inspectionNext ten-year inspection
Fessenheim 1

Fessenheim 1

Year of industrial commissioning

1978

Fessenheim 1

Most recent ten-year inspection

2009

Fessenheim 1

Next ten-year inspection

n/a

Fessenheim 1

Units

Gravelines 6

Fessenheim 1

Year of industrial commissioning

1985

Fessenheim 1

Most recent ten-year inspection

2018

Fessenheim 1

Next ten-year inspection

VD4

Fessenheim 2

Fessenheim 2

Year of industrial commissioning

1978

Fessenheim 2

Most recent ten-year inspection

2011

Fessenheim 2

Next ten-year inspection

n/a

Fessenheim 2

Units

Cruas 3

Fessenheim 2

Year of industrial commissioning

1984

Fessenheim 2

Most recent ten-year inspection

2014

Fessenheim 2

Next ten-year inspection

VD4

Bugey 2

Bugey 2

Year of industrial commissioning

1979

Bugey 2

Most recent ten-year inspection

2010

Bugey 2

Next ten-year inspection

VD4

Bugey 2

Units

Cruas 4

Bugey 2

Year of industrial commissioning

1985

Bugey 2

Most recent ten-year inspection

2016

Bugey 2

Next ten-year inspection

VD4

Bugey 3

Bugey 3

Year of industrial commissioning

1979

Bugey 3

Most recent ten-year inspection

2013

Bugey 3

Next ten-year inspection

VD4

Bugey 3

Units

Chinon B3

Bugey 3

Year of industrial commissioning

1987

Bugey 3

Most recent ten-year inspection

2009

Bugey 3

Next ten-year inspection

VD3

Bugey 4

Bugey 4

Year of industrial commissioning

1979

Bugey 4

Most recent ten-year inspection

2011

Bugey 4

Next ten-year inspection

VD4

Bugey 4

Units

Chinon B4

Bugey 4

Year of industrial commissioning

1988

Bugey 4

Most recent ten-year inspection

2010

Bugey 4

Next ten-year inspection

VD3

Bugey 5

Bugey 5

Year of industrial commissioning

1980

Bugey 5

Most recent ten-year inspection

2011

Bugey 5

Next ten-year inspection

VD4

Bugey 5

Units

Paluel 1

Bugey 5

Year of industrial commissioning

1985

Bugey 5

Most recent ten-year inspection

2016

Bugey 5

Next ten-year inspection

VD4

Dampierre 1

Dampierre 1

Year of industrial commissioning

1980

Dampierre 1

Most recent ten-year inspection

2011

Dampierre 1

Next ten-year inspection

VD4

Dampierre 1

Units

Paluel 2

Dampierre 1

Year of industrial commissioning

1985

Dampierre 1

Most recent ten-year inspection

2018

Dampierre 1

Next ten-year inspection

VD4

Gravelines 1

Gravelines 1

Year of industrial commissioning

1980

Gravelines 1

Most recent ten-year inspection

2011

Gravelines 1

Next ten-year inspection

VD4

Gravelines 1

Units

Paluel 3

Gravelines 1

Year of industrial commissioning

1986

Gravelines 1

Most recent ten-year inspection

2017

Gravelines 1

Next ten-year inspection

VD4

Gravelines 2

Gravelines 2

Year of industrial commissioning

1980

Gravelines 2

Most recent ten-year inspection

2013

Gravelines 2

Next ten-year inspection

VD4

Gravelines 2

Units

Paluel 4

Gravelines 2

Year of industrial commissioning

1986

Gravelines 2

Most recent ten-year inspection

2019

Gravelines 2

Next ten-year inspection

VD4

Tricastin 1

Tricastin 1

Year of industrial commissioning

1980

Tricastin 1

Most recent ten-year inspection

2019

Tricastin 1

Next ten-year inspection

VD5

Tricastin 1

Units

Saint-Alban 1

Tricastin 1

Year of industrial commissioning

1986

Tricastin 1

Most recent ten-year inspection

2017

Tricastin 1

Next ten-year inspection

VD4

Tricastin 2

Tricastin 2

Year of industrial commissioning

1980

Tricastin 2

Most recent ten-year inspection

2011

Tricastin 2

Next ten-year inspection

VD4

Tricastin 2

Units

Flamanville 1

Tricastin 2

Year of industrial commissioning

1986

Tricastin 2

Most recent ten-year inspection

2018

Tricastin 2

Next ten-year inspection

VD4

Dampierre 2

Dampierre 2

Year of industrial commissioning

1981

Dampierre 2

Most recent ten-year inspection

2012

Dampierre 2

Next ten-year inspection

VD4

Dampierre 2

Units

Saint-Alban 2

Dampierre 2

Year of industrial commissioning

1987

Dampierre 2

Most recent ten-year inspection

2018

Dampierre 2

Next ten-year inspection

VD4

Dampierre 3

Dampierre 3

Year of industrial commissioning

1981

Dampierre 3

Most recent ten-year inspection

2013

Dampierre 3

Next ten-year inspection

VD4

Dampierre 3

Units

Flamanville 2

Dampierre 3

Year of industrial commissioning

1987

Dampierre 3

Most recent ten-year inspection

2008

Dampierre 3

Next ten-year inspection

VD3

Dampierre 4

Dampierre 4

Year of industrial commissioning

1981

Dampierre 4

Most recent ten-year inspection

2014

Dampierre 4

Next ten-year inspection

VD4

Dampierre 4

Units

Cattenom 1

Dampierre 4

Year of industrial commissioning

1987

Dampierre 4

Most recent ten-year inspection

2016

Dampierre 4

Next ten-year inspection

VD4

Tricastin 3

Tricastin 3

Year of industrial commissioning

1981

Tricastin 3

Most recent ten-year inspection

2012

Tricastin 3

Next ten-year inspection

VD4

Tricastin 3

Units

Cattenom 2

Tricastin 3

Year of industrial commissioning

1988

Tricastin 3

Most recent ten-year inspection

2018

Tricastin 3

Next ten-year inspection

VD4

Tricastin 4

Tricastin 4

Year of industrial commissioning

1981

Tricastin 4

Most recent ten-year inspection

2014

Tricastin 4

Next ten-year inspection

VD4

Tricastin 4

Units

Nogent 1

Tricastin 4

Year of industrial commissioning

1988

Tricastin 4

Most recent ten-year inspection

2019

Tricastin 4

Next ten-year inspection

VD4

Gravelines 3

Gravelines 3

Year of industrial commissioning

1981

Gravelines 3

Most recent ten-year inspection

2012

Gravelines 3

Next ten-year inspection

VD4

Gravelines 3

Units

Belleville 1

Gravelines 3

Year of industrial commissioning

1988

Gravelines 3

Most recent ten-year inspection

2010

Gravelines 3

Next ten-year inspection

VD3

Gravelines 4

Gravelines 4

Year of industrial commissioning

1981

Gravelines 4

Most recent ten-year inspection

2014

Gravelines 4

Next ten-year inspection

VD4

Gravelines 4

Units

Belleville 2

Gravelines 4

Year of industrial commissioning

1989

Gravelines 4

Most recent ten-year inspection

2019

Gravelines 4

Next ten-year inspection

VD4

Blayais 1

Blayais 1

Year of industrial commissioning

1981

Blayais 1

Most recent ten-year inspection

2012

Blayais 1

Next ten-year inspection

VD4

Blayais 1

Units

Nogent 2

Blayais 1

Year of industrial commissioning

1989

Blayais 1

Most recent ten-year inspection

2010

Blayais 1

Next ten-year inspection

VD3

Blayais 2

Blayais 2

Year of industrial commissioning

1983

Blayais 2

Most recent ten-year inspection

2013

Blayais 2

Next ten-year inspection

VD4

Blayais 2

Units

Penly 1

Blayais 2

Year of industrial commissioning

1990

Blayais 2

Most recent ten-year inspection

2011

Blayais 2

Next ten-year inspection

VD3

Blayais 3

Blayais 3

Year of industrial commissioning

1983

Blayais 3

Most recent ten-year inspection

2015

Blayais 3

Next ten-year inspection

VD4

Blayais 3

Units

Cattenom 3

Blayais 3

Year of industrial commissioning

1991

Blayais 3

Most recent ten-year inspection

2011

Blayais 3

Next ten-year inspection

VD3

Blayais 4

Blayais 4

Year of industrial commissioning

1983

Blayais 4

Most recent ten-year inspection

2015

Blayais 4

Next ten-year inspection

VD4

Blayais 4

Units

Golfech 1

Blayais 4

Year of industrial commissioning

1991

Blayais 4

Most recent ten-year inspection

2012

Blayais 4

Next ten-year inspection

VD3

Saint-Laurent 1

Saint-Laurent 1

Year of industrial commissioning

1983

Saint-Laurent 1

Most recent ten-year inspection

2015

Saint-Laurent 1

Next ten-year inspection

VD4

Saint-Laurent 1

Units

Cattenom 4

Saint-Laurent 1

Year of industrial commissioning

1992

Saint-Laurent 1

Most recent ten-year inspection

2013

Saint-Laurent 1

Next ten-year inspection

VD3

Saint-Laurent 2

Saint-Laurent 2

Year of industrial commissioning

1983

Saint-Laurent 2

Most recent ten-year inspection

2013

Saint-Laurent 2

Next ten-year inspection

VD4

Saint-Laurent 2

Units

Penly 2

Saint-Laurent 2

Year of industrial commissioning

1992

Saint-Laurent 2

Most recent ten-year inspection

2014

Saint-Laurent 2

Next ten-year inspection

VD3

Chinon B1

Chinon B1

Year of industrial commissioning

1984

Chinon B1

Most recent ten-year inspection

2013

Chinon B1

Next ten-year inspection

VD4

Chinon B1

Units

Golfech 2

Chinon B1

Year of industrial commissioning

1994

Chinon B1

Most recent ten-year inspection

2014

Chinon B1

Next ten-year inspection

VD3

Cruas 1

Cruas 1

Year of industrial commissioning

1984

Cruas 1

Most recent ten-year inspection

2015

Cruas 1

Next ten-year inspection

VD4

Cruas 1

Units

Chooz B1

Cruas 1

Year of industrial commissioning

2000

Cruas 1

Most recent ten-year inspection

2010

Cruas 1

Next ten-year inspection

VD2

Chinon B2

Chinon B2

Year of industrial commissioning

1984

Chinon B2

Most recent ten-year inspection

2016

Chinon B2

Next ten-year inspection

VD4

Chinon B2

Units

Chooz B2

Chinon B2

Year of industrial commissioning

2000

Chinon B2

Most recent ten-year inspection

2019

Chinon B2

Next ten-year inspection

VD3

Cruas 2

Cruas 2

Year of industrial commissioning

1984

Cruas 2

Most recent ten-year inspection

2018

Cruas 2

Next ten-year inspection

VD4

Cruas 2

Units

Civaux 1

Cruas 2

Year of industrial commissioning

2002

Cruas 2

Most recent ten-year inspection

2011

Cruas 2

Next ten-year inspection

VD2

Gravelines 5

Gravelines 5

Year of industrial commissioning

1985

Gravelines 5

Most recent ten-year inspection

2017

Gravelines 5

Next ten-year inspection

VD4

Gravelines 5

Units

Civaux 2

Gravelines 5

Year of industrial commissioning

2002

Gravelines 5

Most recent ten-year inspection

2012

Gravelines 5

Next ten-year inspection

VD2

Of note in 2019 is the success of ten-year inspection no. 4 (VD4) on the Tricastin unit (see section 1.4.1.1.5 “Preparing for the future of the nuclear fleet in France”). The unit was decoupled on 1 June 2019 and diverged after the ten-year inspection on 19 December 2019. The VD2 ten-year inspection of the Chooz B2 unit, decoupled on 15 March 2019 and re-coupled after the ten-year visit on 6 August 2019, was also successful.

(1) Excluding Cottam
(2) These amounts include production and capactiy outside the Italian market.